Edmonton Fibre-to-the-Home Expansion

Edmonton & Sherwood Park, AB14 Months
Concrete cutting and utility exposure for fibre optic installation

FTTP Rollout — Directional Drilling, Conduit Placement & Fibre Splicing

The Challenge

A major telecom provider needed to rapidly expand fibre-to-the-home coverage across high-density residential neighbourhoods in southeast Edmonton and Sherwood Park. The project required navigating congested existing utility corridors, minimizing disruption to homeowners, and meeting aggressive 'homes passed' targets on a tight timeline.

Our Solution

Top Civil deployed multiple directional drilling crews equipped with Vermeer 10x15 and 20x22 rigs, paired with hydrovac units for utility daylighting. Our integrated approach allowed us to drill, place conduit, and splice fibre with a single point of contact — eliminating costly hand-offs between separate subcontractors.

Results

  • 500+ homes passed within 14 months
  • Zero utility strikes across the entire project
  • 12% ahead of schedule at final completion
  • 98.7% first-pass OTDR test success rate
HydrovacDeep UtilityIndustrialCalgary

Calgary Industrial Hydrovac & Utility Repair

Calgary Industrial District, AB6 Months
Hydrovac truck performing precision excavation at Calgary industrial site

Non-Destructive Excavation — Hydrovac Daylighting & Deep Utility Repair

The Challenge

An energy sector client required precision hydro-excavation and deep utility repair services within a high-risk industrial facility south of Calgary. Existing underground infrastructure was poorly documented, creating significant strike risk for conventional excavation methods.

Our Solution

Our Rival T7 hydrovac units were deployed to safely daylight and expose buried utilities before any mechanical excavation began. Once all existing infrastructure was verified and mapped, our civil crews completed the deep utility repairs with zero incidents.

Results

  • 200+ utility exposures completed with zero incidents
  • Complete as-built utility mapping delivered to client
  • 40% reduction in total excavation time vs. conventional methods
  • Full compliance with Alberta OHS standards
CivilRoadworksMunicipalRed Deer

Central Alberta Municipal Infrastructure Build

Red Deer & Lacombe County, AB18 Months
Road construction and utility installation in Central Alberta subdivision

Full Subdivision Development — Deep Utilities, Road Construction & Servicing

The Challenge

A growing Central Alberta municipality needed a full-service civil contractor to take a new residential subdivision from raw land to fully serviced lots. The project required deep utility installation (sanitary, storm, water), complete road construction, and integration with the existing municipal infrastructure network.

Our Solution

Top Civil managed the entire project lifecycle from initial surveying through to final grading. Our vertically integrated structure allowed us to self-perform excavation, pipe laying, backfill, road sub-base preparation, and curbing — avoiding the scheduling conflicts common when juggling multiple subcontractors.

Results

  • 85 fully serviced residential lots delivered
  • 4.2 km of underground utility installation
  • Complete road network with curbing and stormwater management
  • Project delivered on-budget and 3 weeks ahead of schedule
Questions

Case Study FAQs

Yes. We are happy to provide references from past and current clients upon request. Please contact us directly and we will connect you with relevant project stakeholders.

We handle projects ranging from small residential utility installations to multi-million-dollar municipal subdivision builds and large-scale fibre rollouts. Our vertically integrated structure allows us to scale crews and equipment efficiently.

Our primary service area covers the Edmonton–Calgary corridor including Red Deer, Sherwood Park, St. Albert, Spruce Grove, Leduc, Airdrie, and Cochrane. We also take on projects throughout Alberta and into Saskatchewan.

Ready to Be Our Next Success Story?

Contact us to discuss how Top Civil can deliver results for your Edmonton, Calgary, or Central Alberta project.

Top Civil Assistant

Trained on our full website

Hi there! 👋 I'm the Top Civil Construction assistant. I'm trained on all our services, project areas, careers, safety practices, and more. Try a suggestion below or ask me anything!